    Dear all ,

    We are in weighted average date in Retail scenario with more than 1800 stores.
    do you recommend to set scheduled inventory recalculation ?
    as you know recalculation takes a lot of time in this costing method with a lot of volume transactions .

    What do we have react with this type of costing method in recalculation and closing period ?

    With Regards,

    ------------------------------
    Kajal Solgi
    Ofogh
    ------------------------------
    Conference-AXUG_200x200


  • 2.  RE: Scheduleing Inventory recalculation

    GOLD CONTRIBUTOR
    Posted 25 days ago
    Kajal,

    I'd recommend a daily recalculation that runs at night in a batch job. The more frequently it is run, the shorter it will take to run.

    ------------------------------
    Ian Gorman, PMP, MCSE
    Senior Consultant
    ------------------------------

    Conference-AXUG_200x200


  • 3.  RE: Scheduleing Inventory recalculation

    Posted 24 days ago
    Dear Lan, 

    Thank you so much for reply .but , running recalculation nightly takes a lot of time for weighted average date .
    as I know when I run recalculation , the system revers the previous recalculation and run it again , then it will take lots of time .

    With Regards,

    ------------------------------
    Kajal Solgi