Another option you might consider is an outside processing item on a production order. The setup is more complex than a charge code, and probably isn't worth it if you're not already using production. The advantage it provides is two separate purchase orders; one for the raw part and one for the engraving service. Here's what you would need to do this:
- Setup
- Item number for raw part
- Item number for engraved part
- Item number for engraving service
- Bill of material that has the raw part and the engraving service as components of the engraved part.
- Process
- Create a production order for the engraved part. This creates a purchase order for the engraving service automatically.
- Create and receive a purchase order for the raw part. The raw part should still be shipped to vendor B. The receipt will allow you to invoice the purchase order to vendor A.
- Vendor B engraves the raw part and ships it to you.
- Receive the purchase order for the engraving service. This allows the purchase order for vendor B to be invoiced.
- Report the production order as finished. This puts the engraved part into inventory.
The process is more complicated than adding a charge code, but provides better information on where everything is, and when it will be available. It also gives you two separate purchase orders for your matching and payment process.
------------------------------
Kevin McLean
Strategic Solutions NW
Beaverton OR
------------------------------
Original Message:
Sent: Feb 09, 2021 10:50 AM
From: Rod Helmick
Subject: Additional Costs for an Item when Purchasing
I have a situation where I want to add a service cost to my item that is ordered on a PO. For example, I have item XYX and I purchase it from Vendor A. Vendor A sends the product over to another Vendor B who performs a service (in this case, engraving) on the item. Once that service is completed, Vendor B sends the product to us so we can then receive that PO. I'm not sure the best way to depict this on a setup situation within D365. I want the cost of the service to be included in the overall cost of the product. So if my product cost from Vendor A is $10 and Vendor B is an additional $2 for engraving, the overall cost of the item when received into Inventory should reflect $12. I also want to be able to invoice and pay each vendor appropriately, $10 going to Vendor A, and $2 going to Vendor B. Anyone come across this in their current environment and/or have any suggestions on how we can resolve this?
Thanks,
------------------------------
Rod Helmick
RTHGlobal, Inc
Cave Creek
------------------------------