Operation Starts after previous operation ends

  • 1.  Operation Starts after previous operation ends

    Posted Mar 27, 2015 02:33 AM

    Hi,

    There is a requirement that while processing production order the next operation will be started after the previous operation in the route is ended. Also if the previous operation is completed partially then the next operation will be started with quantity completed in  previous.

    Also someone told me that set the link type on the route operation screen to hard but it wont work.

    Any suggestion how to get this done.

    ------------------------------